Renovation, phase 2 is about to start!

Phase 1 is well underway, and we will all be moving upstairs in preparation for Sunday, July 1st, and the start of the renovation on the 1st floor.  You will notice when we move upstairs, that not everything will be in place or complete.  It will be fun to come back each Sunday, to see what they have accomplished during the work week.

They will start 1st floor work on Monday July 2 on ceilings, lighting, paint, carpet, tile, and the new Kids Connect entrance!  They will also start the remodel of the Chapel, replace the brick flooring and create the new automated check-in station for Kids Connect.

Beginning July 1 divisions on the EC 1st floor will be relocating to the 2nd floor areas listed below:

  • Toddler / Orange hallway
  • Older Toddler / Blue hallway
  • Young Preschool / Blue hallway
  • Older Preschool / Green hallway
  • Kindergarten / Orange hallway
  • 1st-3rd grade / Orange hallway

Informational cards with maps and locations will be handed out in all classrooms June 24 - July 15.

Grades 4 and 5 will remain in their current location during the entire renovation.

The entire renovation is scheduled to be completed by the end of August. We anticipate all divisions returning to their permanent location by Promotion Sunday, August 19.

Thanks so much in advance for your patience and cooperation with these changes this summer. It will be worth the effort, as the changes will be new and exciting! 

Shelley Brooks

CCC Director of Early Childhood Ministry

Previous
Previous

Update on the renovation in the Education Center

Next
Next

Renovation of the Education Center (EC) is scheduled to begin on May 27!